Comparing Schedules

You can view and compare two animations of the same list of tasks based on different types of start and finish times. For example, you can run the animation set to the Early Start - Early Finish time and then run the same schedule based on the Late Start - Late Finish time and compare the two animations. The Compare Schedules tool creates a new temporary animation similar to the original animation but with the selected type of Start/Finish times. All script entries and tasks in the active animation model are copied for the comparison but are based on the selected Start/Finish times. The temporary model is automatically deleted when you switch to another model or exit the Animation Producer dialog.

You can share schedule linking rules once they are created by the administrator and synchronized to the ConstructSim Work Package Server. (See Automatic Task Linking.) Users can then download the schedule data and linking rules from the server.